City of Kenosha Menu

6th Avenue & 58th Street Resurfacing

On Monday, May 22, 2017 construction began on 6th Avenue and 58th Street. Please see the most recent project update below (dated 9/22/17) for information on the current status of the project.

Click here to view a map of the project location.

For questions regarding this project, please contact Kris Kochman at 262-653-4000.

Additional updates will be posted here as they arise.

Project Update - 9/22/17

6th Avenue- The contractor for the 6th Avenue construction project will be paving the final layer of asphalt and placing pavement markings on Monday, September 25 through Wednesday, September 27. During that time the contractor will close 6th Avenue from 54th Street to Library Park (7th Avenue) to perform this work. Sidewalks will remain open during the road closure for access to businesses. After that period, the traffic control will be reinstalled back to one travel lane and one parking lane, alternating sides of 6th Avenue depending on the work being completed. The remaining work will include crack repairs, landscaping, lighting installation, completion of Friendship Park, and other minor finishing items.

58th Street- The contractor will also close 58th Street from 6th Avenue to 3rd Avenue for paving and pavement markings on Monday, September 25 through Wednesday, September 27. Sidewalks will remain open during the road closure for access to businesses. After that period, the traffic control will be reinstalled back to one travel lane and one parking lane, alternating sides of 58th Street depending on the work being completed. The remaining work will include crack repairs, landscaping, lighting installation, restoration of the storage site, other minor finishing items, and the sidewalk, curb and gutter, lighting, paving, and pavement marking on 58th Street between 6th Avenue and 7th Avenue.

Project Update - 8/14/17

The Kenosha Classic Cruise-In Car Show will be held on 6th Avenue on Saturday, September 2. In order to be ready for this event, the 6th Avenue contractor will be making an extra push during the last few weeks of August. This push will result in the completion of the 6th Avenue sidewalks, brick work and the first of two layers of asphalt pavement being placed on the road. This will provide the event and the businesses a hard surface, free of debris, for the weekend. In order to accomplish this, the contractor will be closing 6th Avenue to traffic from 55th Street to Library Park (7th Avenue) for the week of August 28 through September 1. Sidewalks will remain open for access to businesses. The contractor plans to spend the day of September 1 cleaning up 6th Avenue in preparation for the car show.

After Labor Day weekend, the contractor will continue to work, focusing on the intersection of 6th Avenue and 56th Street, and the south side of 58th Street from 7th Avenue to 3rd Avenue. While their focus will be these two areas, finishing work on 6th Avenue will also continue and may require lane closures and parking restrictions. Access to businesses will be maintained. All major work is anticipated to be completed by the end of September. Minor finishing items are scheduled to be completed within the first two weeks following.

Project Update - 7/31/17

Starting Tuesday, August 1 construction on 6th Avenue will shift to the west side of the road and the traffic pattern through 6th Avenue from 55th Street to Library Park will change. The roadway will remain open to one-way, southbound traffic as it has since the start of this project. The change is that southbound traffic will be traveling in the east lane instead of the west lane. Parking will be allowed on the east side of 6th Avenue (the left side of the road for vehicles traveling southbound). The west lane will be closed, as construction work will be concentrated on that side of the street. All intersections will remain open until reconstruction of each intersection is necessary, at which point there will be closures of individual intersections to allow for construction.
 
Additionally, temporary street lights are being installed on the east side of 6th Avenue. The permanent poles and fixtures will be placed in mid to late August. The City is in the process of refurbishing the existing decorative dual lighting arms and fixtures to be reinstalled on new light poles. The temporary lights are needed to keep some lighting through 6th Avenue while the lights on the west side are taken down, refurbished and prepared for re-installation.

Project Update - 7/5/17

On Thursday, July 6 the intersection of 6th Avenue/6th Avenue A at 59th Street will be closed for a portion of the day in order to perform pavement patching. Additionally, 6th Avenue at 60th Street will be closed for a portion of that day for the same reason. The contractor will not be allowed to have both 59th Street and 60th Street closed at the same time.

Project Update - 6/22/17

The week of June 26th the contractor will begin pouring curb and gutter along 6th Avenue. They will start at 55th Street and work to the south.

Following the curb and gutter, concrete will be poured against the buildings to establish a consistent concrete pad for the rest of the walk to match. This will allow the contractor to bridge the gap area with plywood, allowing businesses to stay open and clientele to navigate to business entrances. Once the pad is complete, light pole bases will be poured and then the contractor will begin pouring the sidewalk.

Project Update - 6/07/17

For the next couple of weeks there may be periodic, short-term closures of 58th Street.

The City of Kenosha Public Works Department has partnered with Quest Construction Data Network.

This is a web-based initiative that will deliver our construction project advertisements and bid documents to you in a more timely and cost effective manner.

Benefits of the electronic delivery of bid documents from QuestCDN include:

  • You may become a member of QuestCDN without cost. You only pay for the bid documents you download.
  • Bid documents can be previewed without cost. You can look over the plan drawings and specifications before deciding whether to download the bid documents.
  • Bid documents will be delivered in the Adobe PDF format so there is no software investment required, just the free Adobe Acrobat Reader program. You can print just the pages you need, helping to reduce paper waste. If addenda are issued, you will be automatically notified by e-mail to return to the web site to access them. Addenda may be downloaded without cost. Plan holder lists and project bid results will be available on the web site.

You may contact QuestCDN at 952-233-1632 or email them at with any questions regarding free membership registration, downloading, or working with the digital bid documents.

Click here to access the Public Works projects currently out for bid - no registration is necessary. Click on the project name to view project details. You may view plans, plan holders and addenda for free.

After bid opening, the results will be shown in the Bid Results tab for the corresponding year.